Makkah Pilgrim Season Parking Structure Marking
Re-mark a 6,200-bay, 6-level pilgrim parking structure serving Makkah accommodation towers ahead of Hajj season, with wayfinding colour coding for non-Arabic-speaking pilgrims, accessibility bays for elderly and disabled pilgrims, and emergency-vehicle access lanes. All work had to be completed before pilgrim arrival.
The Challenge
Re-mark a 6,200-bay, 6-level pilgrim parking structure serving Makkah accommodation towers ahead of Hajj season, with wayfinding colour coding for non-Arabic-speaking pilgrims, accessibility bays for elderly and disabled pilgrims, and emergency-vehicle access lanes. All work had to be completed before pilgrim arrival.
Our Solution
Specified solvent-based acrylic line paint with preformed thermoplastic symbols for high-traffic durability. Layout used zone-coloured levels (yellow, blue, red, green, amber, ivory) for pilgrim wayfinding, with 240 accessibility bays, 120 emergency-vehicle lanes and trilingual (Arabic, English, Urdu) bay-number marking.
Execution
Crews worked 3 shifts per day across 6 levels, applying 6,200 bay lines plus 240 accessibility symbols, 120 emergency-vehicle-lane hatchings and 6 colour-coded level zones. Trilingual bay numbers were stencilled at every bay entry. Final layout was surveyed against Makkah Region Municipality standards.
Project Gallery
βHajj arrival is non-negotiable. Gulf Seismic delivered 9 days early with wayfinding that pilgrims from 180 countries could follow.β
Related projects
Dubai Mega-Mall Parking Deck Marking
Re-mark a 3,200-bay multi-level parking deck without closing the mall, while re-optimising the layout to increase capacity and add EV and family bays.
Abu Dhabi Yas Island Mega-Mall Parking Deck Marking
Re-mark a 5,200-bay multi-level parking deck serving a Yas Island mega-mall without disrupting operations during peak weekend trading. The existing layout had faded bays and no dedicated EV or family parking zones, and the client wanted to add accessibility and EV capacity to meet 2024 sustainability targets.
Dubai Expo City Visitor Parking Lot Marking
Mark a 3,800-bay surface parking lot at the legacy Expo 2020 site (now Expo City Dubai) ahead of its reopening as a permanent visitor destination. The lot required EV, accessibility and family zones plus wayfinding colour coding, with all work completed before opening weekend.
Start your marking project today
Choose the channel that suits you. Our specialists respond within 1 business hour during working days.
Why Gulf Seismic?
- β 10+ years delivering marking projects in the Gulf
- β ISO 9001 certified, RTA & MOMRA compliant
- β ICAO Annex 14 trained aviation crews
- β 850+ projects across 16 cities